Retention Money On Construction Jobs: What It Really Costs You

Last Updated November 2026
The job finished in March. The client signed off, the invoice went in, and almost all of it came through. Almost.
There's still $9,000 sitting somewhere, held as retention until the defects period runs out. Nobody has said no. Nobody has said when, either.
Retention is one of the few places in business where you have done the work, issued the invoice, and still have no money. Here's what holding it actually costs you, when the GST on it is really payable, and how to make sure it comes back.

What Retention Actually Is
Retention is money the party above you holds back from your progress claims as security that you will come back and fix anything that goes wrong. It is not a discount, a penalty, or a deposit. It is your money, held on terms.
How much, and for how long, comes from your contract. In commercial work the common pattern is:
5% of the contract value, often taken as 10% of each early progress claim until the 5% cap is reached
Half released at practical completion, when the job is finished and handed over
The balance released at the end of the defects liability period, which is frequently 12 months after practical completion
None of those numbers are set by law. They are set by whatever you signed.
A Worked Example: One Job, Start To Finish
Say you take on a $180,000 shopfitting subcontract, plus GST, billed across four monthly progress claims. Retention is 5%, half released at practical completion and the balance twelve months later.

Three Key Takeaways
You're funding $9,000 of someone else's security. The $9,900 held is $9,000 plus $900 of GST. If that job carried a 12% net margin — $21,600 — then over 40% of the job's profit is sitting in someone else's account, and about half of it for a year after you finished. You didn't lend it to them deliberately. The contract did it for you.
Your invoicing and your cash never match. You invoiced $49,500 and banked $47,025, four times over. If your cash flow forecast is built off what you invoice, it was wrong by $2,475 a month on this one job.
The GST column doesn't say what the invoice says — $4,275, not $4,500. Which brings us to the next bit.
The GST On Retention: It Waits
Ask around and you'll hear that you pay the GST on retention as soon as you invoice the progress claim and that the ATO takes its cut on money you haven't been paid. It's a reasonable thing to believe, because the general rule for a business that isn't on a cash basis is that GST goes in the BAS for the period you issue the invoice or get paid, whichever comes first.
However for a retention, that general rule doesn't apply. There's a determination covering exactly this: Goods and Services Tax: (Particular Attribution Rules for Retention Payments) Determination 2017 (PAR 2017/2). It splits a progress claim in two:
The part you're actually being paid follows the normal rule — earlier of invoice or payment.
The retention amount is attributed to the earlier of the period the retention is invoiced or the period you receive it.
It's specific about what counts as an invoice for the retention: a document notifying the obligation to pay the retention amount, issued once the contract conditions are met or after the defects liability period has expired. Your original progress claim doesn't start that clock. So in the example above, the $900 of GST inside the retention isn't payable across those four claims. It falls due in two $450 instalments, when each release is invoiced or paid.
Three traps to be mindful of
Your accounting file doesn't know. Raise a tax invoice for the full $49,500 and let the software pick it up the ordinary way, and it reports the full $4,500. You've paid the ATO GST on money you haven't received, up to a year early, when you didn't have to. On one job that's $900. Run six jobs with retention at once and it's $5,400, and it recurs. The determination applies automatically — it's your file that has to keep up, and that means the retention has to be identified as retention.
Late payment isn't retention. The determination applies where the contract lets the other party hold back part of the consideration until conditions are met. A client who simply hasn't paid you is not holding retention, however much it feels like it. There the normal rule applies and the GST is payable as usual.
It goes both ways if you're the one holding it. The rule mirrors for GST credits. If you withhold retention from your subcontractors, your credit on the retained part also waits until it's invoiced or you pay it. Claiming the full credit on a subbie's claim while you're still holding 5% of it is the same error in reverse — and that one goes against you if the ATO ever looks.
What To Actually Do About It
Price for it. If 5% of the job is going to sit with someone else for a year, that's working capital you're lending interest-free. It belongs in your margin, not in your hope.
Track retention as its own line. Not buried in trade debtors. A separate "Retention receivable" account, with the job, the amount and both release dates against it. If it isn't on a list with a date, it doesn't get chased.
Check how your file handles the GST. Is the retention split out, or is the whole progress claim going through as one amount? This is the most common place we see businesses paying GST earlier than they need to — and where builders holding subbie retention over-claim credits.
Diarise both release dates. Practical completion and the end of the defects liability period. Set a reminder two weeks before each and invoice on the day it falls due.
Ask about a bank guarantee instead of cash retention. On a bigger job it's worth raising. A guarantee leaves the cash in your business instead of someone else's account, which is the whole problem in one move. It isn't free and not every head contractor will agree, but nobody offers if you don't ask. Swapping doesn't buy you a tax deferral either: the amount assessable to you doesn't drop because a guarantee replaced the cash.
Read the retention clause before you sign. How much, what triggers each release, who has to do what, and whether the defects period starts at practical completion or somewhere later. A 24-month defects period on a thin-margin job is a different job.
Our post on how much cash buffer your business should actually hold is a good companion to this one, because retention is one of the things that buffer is quietly covering.
Know What You're Owed
If you're carrying retention across several jobs and couldn't say today what the total is, when each piece falls due, or whether you've already paid the GST on it, that's the place to start. We can set up the tracking, get the GST and tax timing working with your cash flow instead of against it, and build the retention drag into how you price the next job.
General information only – speak to your accountant about your situation.
Frequently Asked Questions
What is retention money in a construction contract?
Retention is a portion of each progress payment held back by the party above you as security that you'll return and rectify defects. It's commonly 5% of the contract value, with about half released at practical completion and the balance at the end of the defects liability period. The amount and timing come from your contract, not from legislation.
Do I have to pay GST on retention before I receive it?
Generally no. Under PAR 2017/2, GST on a retention amount is attributed to the earlier of the period the retention is invoiced or the period you receive it — not the period you issued the original progress claim. The catch is that your accounting file has to treat the retention as retention; if the full progress claim is reported as one amount, you'll pay the GST early.
When is GST on retention actually payable?
When you invoice the retention or receive it, whichever comes first. The determination defines an invoice for the retention amount as a document notifying the obligation to pay it, issued once the contract conditions are met or after the defects liability period has expired.
Can I claim the GST credit on retention I'm holding from a subcontractor?
Not until they invoice the retention or you pay it. The rule mirrors the supply side, so claiming the full credit while you still hold the retention over-claims it.
Is retention money taxable income before it's released?
Generally not. Where the work runs beyond one income year, TR 2018/3 — the ATO's ruling on long term construction contracts — says retention amounts aren't assessable until you receive them or become entitled to receive them. On a job that starts and finishes inside one income year that ruling doesn't apply, but the answer is usually the same, because income isn't derived until it's actually due to you.